by in News

Šahmanović: Montenegro expects first large private wind and solar plants to be online in 2026

Over the past year, Montenegro has adopted two reform laws – on energy and on renewable energy sources – and scheduled its first auctions for market premiums. Admir Šahmanović, Minister of Energy and Mining, told Balkan Green Energy News that the new regulations fully align the sector with the European Union acquis, sending a clear signal to investors that Montenegro now has a stable regulatory framework and market-based prices that safeguard citizens’ interests. Becoming part of the European energy space, he added, is not only a political goal but also the path Montenegro should follow to ensure cleaner and more secure energy for future generations.

Admir Šahmanović served as Minister of Mining, Oil and Gas in the government of Prime Minister Milojko Spajić. In February this year, he became the coordinator of the Ministry of Energy, and since April, he has served as Montenegro’s Minister of Energy and Mining. In an interview with Balkan Green Energy News, Šahmanović discusses his plans to mobilize larger investments, Montenegro’s timeframe for coupling its electricity market with Italy and the EU, the ministry’s steps to prepare the country for the EU’s carbon border tax, and plans for investments in the natural gas sector.

What are the key innovations introduced by Montenegro’s law on renewable energy sources?

The law on renewable energy sources introduced, for the first time, a clear, competitive and fully transparent support mechanism for green energy production – an auction scheme.

Over the past months, we have worked hard to ensure the law really takes hold. We have prepared about 15 by-laws that enabled us to launch the first auctions. I believe this is one of the most important contributions of the new law, as it sends a clear message to investors that Montenegro has a stable framework and market-based prices that safeguard citizens’ interests.

In this way, we are laying a solid foundation for a rapid energy transition, which is both our strategic choice and our responsibility to future generations.

Montenegro has also adopted a new law on energy. What does this regulation bring?

The Law on Energy is our umbrella regulation, providing a framework that fully aligns the sector with the EU acquis. It introduces stricter standards, greater protection of end consumers, better competition, and stronger institutional oversight.

It also opens Montenegro’s energy sector to the European market and creates a stable, predictable environment. This is important not only for investors but also for all consumers, as people are ultimately the ones affected by any change in the system.

You stated that these reforms set a clear strategic path for Montenegro, which sees its energy future within the European market. What will this future bring to Montenegro, its economy, and its citizens?

Our ambition is to make Montenegro a country with clean energy and a stable system. Being part of the European energy space ensures greater security of supply, lower costs in the long term, and a strong inflow of investments. Our economy will have access to a larger market, and our citizens will benefit from safe, sustainable, and environmentally friendly energy.

It is not just a political goal – it is a path I want us to follow in our development, so that we leave our children a country with cleaner and more secure energy.

Admir Šahmanović visiting northern Montenegro with EPCG Director Ivan Bulatović

Applications have been invited for Montenegro’s first auctions for market premiums. What benefits do you expect from auctions?

The auction mechanism allows us to select the most favorable and serious investors through a fair and competitive process. Projects are implemented without budget subsidies and with minimal risk to the state.

We expect auctions to ensure new capacities, create jobs, improve the use of our natural resources, and strengthen overall energy stability. These are the benefits citizens will feel, both on their electricity bills and through new opportunities that will open up in local communities.

Investor interest in wind and solar is strong, with requests to build power plants totaling around 5.5 GW. When do you expect these projects to be realized?

Such strong interest is the best proof that the reforms are yielding results. We expect the first large projects to be online in 2026, with significant capacities ready by 2030. Transparent procedures, good cooperation with local communities, and improved grid infrastructure will be key to making these investments a reality.

What are the main obstacles to these projects? How to remove them?

The biggest challenges are administrative procedures, transmission network limitations, and spatial planning documents. We are working to address them through interdepartmental cooperation, digitalization of processes, and the state’s commitment.

We are strengthening capacities, speeding up permitting, and modernizing regulations. I want to ensure that investors coming to Montenegro know they can work in a clear, predictable, and fair environment.

Admir Šahmanović at the ministerial panel at Belgrade Energy Forum 2025 in May

Preparations are underway to link Montenegro’s electricity market with the EU via Italy, with 2027 featuring as the target year.

Yes, we are working diligently on institutional and market integration. This involves harmonizing the rules, passing the remaining by-laws, and preparing the market operator. With the support of the EU and the Energy Community, I am confident that 2027 will remain the year when we will fully open our market to Europe.

All countries in the region are facing CBAM. How prepared is Montenegro?

CBAM will change the rules for electricity exports to the EU, bringing new costs as well as opportunities. We are aware that it will be a financial burden on our economy, but that is precisely why we view it as an additional incentive to accelerate the implementation of renewable energy projects and increase our own production of green electricity.

We are working on adjusting the regulatory framework, harmonizing economic activities, and ensuring the largest possible share of clean energy to remain competitive and maintain full access to the European market while reducing emissions.

Montenegro also has ambitious plans in the natural gas sector – a gas pipeline, a terminal for liquefied natural gas (LNG), and gas-fired power plants. How far along are these projects?

I see gas as a development opportunity – to ensure greater security of supply, diversification, and new opportunities for the economy. But I also believe that such strategic projects must be developed through dialogue with local communities, with full respect for their views.

We are currently preparing and developing the Ionian Adriatic Pipeline (IAP) project and assessing the potential for an LNG terminal. We are doing this responsibly, one step at a time, and in line with the EU’s energy transition goals.

by in News

RP Global gets EUR 12.2 million loan for Novalja solar project

RP Global has secured a EUR 12.2 million loan to build its Novalja solar power plant in Croatia.

In late April, Austrian company RP Global began the construction of the Novalja photovoltaic plant at the Zaglava site on the island of Pag.

The European Bank for Reconstruction and Development (EBRD) said it approved a senior non-recourse project finance loan of up to EUR 12.2 million to RP Global Novalja d.o.o., owned by RP Global Energy GmbH, for the development and construction of the 21 MW Novalja PV plant in Croatia.

The project has been approved under the EBRD InvestEU Framework for Sustainable Transition.

The loan is divided into two tranches

The loan is split into two tranches: one amounting to a maximum of EUR 7.2 million, and the second of up to EUR 5 million, benefiting from a 20% first loss coverage under the EBRD InvestEU Framework for Sustainable Transition, the bank’s decision reads.

The total project cost is estimated at EUR 16.3 million.

The endeavor includes the installation of 35,776 photovoltaic panels. The expected annual electricity production is around 31,000 MWh, enough to supply about 12,000 households.

According to the EBRD, the project supports innovative offtake arrangements. It will combine a national renewables support with a merchant exposure in later years.

RP Global won premiums for its project at auctions

Last July, the Croatian Energy Market Operator (HROTE) awarded premiums for solar and hydropower plants with a total capacity of 420 MW. RP Global’s Novalja was among them, with 15 MW.

Back in 2022, the company said it intended to build wind farms and solar parks of 500 MW overall in Croatia over the next five years.

RP Global has completed two renewable energy projects in Croatia: the Danilo wind farm near Šibenik and the Rudine wind park near Dubrovnik.

Of note, the island town of Novalja could become one of the first in Croatia to begin the production of green hydrogen, and a rare example in the region. A project was launched in May.

by in News

Serbia allocates entire quota at second auctions, investors to install 645 MW of wind, solar

Serbia allocated the entire 424.8 MW quota in its second wind and solar power auction. According to the Ministry of Mining and Energy, the winning bids came from investors from China, the United States, France, and Serbia. They intend to install ten power plants with a total capacity of 645 MW.

The Ministry of Mining and Energy conducted the second round of renewable electricity auctions. Forty-one applications were submitted for market premiums, and 37 were declared valid. Both segments were oversubscribed. Investors in wind submitted bids for 444 MW, and the quota was 300 MW. For solar, they applied for premiums for 260 MW, compared to the available 124.8 MW.

The winners have the right to sign 15-year contracts for difference (CfDs).

Seven bids were declared valid for wind, and five filled the quota. Investors will build wind parks with an overall capacity of 468 MW, and premiums will be awarded for 300 MW, according to the proposed ranking list, published on the ministry’s website, which tracks renewable energy tender procedures. The maximum acceptable bid for wind farms was EUR 79 per MWh, and the investors offered from EUR 53.59 to EUR 68.25, according to the announcement.

These are the winning bidders: Matrix Power, owned by French developer Akuo Energy, Windvision Windfarm A, Windvision Windfarm B, Crni Vrh Power, owned by Chinese companies Shanghai Electric Power & Energy Development Limited and CMC Capital, and Jasikovo, owned by Serbian citizens.

The crowd was much bigger for the solar segment. Five projects won the right to market premiums. A total of 30 applications were valid. The quota was 124.8 MW, and the selected investors are set to install photovoltaic plants with 177 MW in combined capacity, the ministry’s proposed ranking list shows.

It said that the investors offered prices from EUR 50.9 to EUR 59 per MWh. The ceiling for electricity from photovoltaic plants was EUR 72. The following firms had winning bids: Vemi Biogas, Kobra Global, Solarina, Mona Green Energy 2, and Brankov Solar. The 150 MW Solarina project is the only large one, while Brankov Solar is an agrisolar one.

Solarina is owned by CWP Europe, and Mona Green Energy 2 by Serbia’s Mona Holding. The three other firms are owned by Serbian citizens.

The ministry noted that the total planned investments of the winning bids is EUR 782 million.

Đedović Handanović: All produced electricity will be offtaken by Serbia’s utility EPS

Minister Dubravka Đedović Handanović said the second round of auctions was highly successful in capacity and offered prices. Importantly, all electricity from the power plants that get the premiums will go to state-owned power utility Elektroprivreda Srbije (EPS) and be used to supply domestic businesses and households.

“The offered prices are very competitive, i.e. EUR 50.9 per MWh for solar and EUR 53.5 per MWh for wind, which is significantly below the market levels. According to our incentives model, this means we don’t expect power plants will be subsidized but that they will return windfall profit to the state as long as market prices are higher than those offered by the auction winners,” she stated.

The confirmation of good conditions for investment in Serbia

Đedović Handanović stressed that the high interest by investors is a confirmation of good conditions for investments in Serbia.

“In addition to domestic investors, the winners of these auctions are also investors from China, the USA, and France. It demonstrates that Serbia is globally recognized as a good destination for investment, which will be very significant in achieving our strategic goals in the energy transition process,” she said.

In 2023, the Government of Serbia adopted the incentives plan for renewables for a three-year period through 2025. It said it would award market premiums for 1.3 GW. The first round of auctions was conducted in 2023. The selected projects, for 715 MW in total capacity, are all supposed to be connected to the grid by the end of next year.