Applications open for first wind power auction in Kosovo*

The Ministry of Economy of Kosovo* invited the three prequalified entities to submit bids for a wind power auction for a targeted capacity of up to 100 MW. The authorities didn’t declare any deadline.

Eight months after the prequalifications process was completed, when Minister of Economy Artane Rizvanolli said the next phase would start soon, eligible bidders can now submit proposals within the first wind power auction in Kosovo*. They are France-based Akuo Energy, consortium of Notus Energy from Germany and domestic firm Stublla Energy, and a consortium led by Güri̇ş, headquartered in Turkey.

The prequalifications call was launched one whole year ago. The Ministry of Economy said it intends to award up to 100 MW. According to earlier updates, the plan is to support 150 MW in total in two rounds. Participants will bid for 15-year power purchase agreements (PPAs) and contracts for difference (CfDs).

Maximum bidding price is EUR 80.2 per MWh

Interestingly, no deadline was published in the announcement. Rizvanolli earlier said the request for proposals would last half a year.

The lowest price per megawatt-hour wins and the upper limit is EUR 80.2 per MWh.

Investments envisaged as public-private partnerships

Wind projects would be run by special purpose vehicles (SPVs), firms where the government would have a share of up to 49%, as per initial documentation. The Ministry of Economy intended to use the funds from the International Monetary Fund’s Resilience and Sustainability Facility (RSF) in the development of the 150 MW.

The purpose of the public-private partnership scheme is to reduce risk for the private investors. They will be obligated to design, build, operate, maintain and decommission wind parks.

Balancing responsibility is limited to imbalance volumes greater than 10%. Curtailment is subject to financial compensation.

Funded by Germany, International Finance Corp. – IFC, which is part of World Bank Group, has provided support for organizing the first wind power auction in Kosovo*, alongside the now defunct United States Agency for International Development (USAID), Luxembourg Development Cooperation Agency – LuxDev, and the European Bank for Reconstruction and Development (EBRD).

Kosovo* hosts just three wind power facilities: Selac, also known as Bajgora (104.1 MW), Kitka (32.4 MW) and Golesh (1.35 MW).

The first solar power auction was held last year.

* This designation is without prejudice to positions onstatus and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
by in News

Simtel to install BESS for Güriş in Romania

Romanian engineering and technology company Simtel will install a battery energy storage system in Romania for Turkey-based Güriş.

With a storage capacity of up to 196.4 MWh and an installed power of up to 98.6 MW, it would be one of the largest battery energy storage systems (BESS) in Romania.

Simtel said it signed an engineering, procurement, and construction contract with Energy Capital Group, owned by Mogan Bucharest SRL, part of the Güriş Group from Turkey.

The contract is worth RON 168.9 million (EUR 33.3 million), and the deadline is nine months.

The contract includes the supply of a BESS, the design, construction, installation, commissioning, completion, and testing of the facility. The project will be implemented in the village of Iaz, Obreja commune, Caraș-Severin county.

Energy Capital Group obtained support via the National Recovery and Resilience Plan

Energy Capital Group received support via the National Recovery and Resilience Plan (NRRP) for its project. It is part of the pillar dedicated to the green transition. Romania approved a grant of over RON 50 million (EUR 9.86 million) for the implementation of the battery energy storage project.

With the investment, Romania is taking a significant step towards strengthening its energy infrastructure and increasing flexibility in consumption and production, according to Simtel COE Mihai Tudor. Storage systems are an essential pillar of the energy transition process and in the sustainable development of power grids, he added.

Director of Mogan Bucharest SRL Kaan Yamantürk said the company sees “a great future and opportunity” in Romania.

Güriş is active elsewhere in Southeastern Europe as well.

Simtel: The largest storage project has a capacity of 72 MWh

Simtel pointed out that the size of the facility is significant, considering that, according to the latest data published by Transelectrica, the current total battery energy storage capacity in Romania is 398.8 MWh.

Moreover, the largest storage project completed so far has a maximum capacity of 72 MWh, the firm added.

Of note, in October last year, Monsson said it was completing the second phase of a battery energy storage system within a hybrid power plant project in Constanța. The first phase was inaugurated in April and, with 24 MWh, it was the largest BESS unit in Romania at the time.

A subsidiary of Monsson has submitted a battery storage project of just over 2 GWh in capacity for an environmental permit in Romania. Simtel and Monsson have signed a strategic partnership on the development of solar and energy storage projects in Romania.

by in News

Kosovo* completes first solar power auction at EUR 48.88 per MWh

A consortium led by Switzerland-based construction company Orllati was selected to build and operate a solar park of up to 105 MW in connection capacity for 30 years including a 15-year contract for difference. The group won the first renewable electricity auction in Kosovo* with a bid of EUR 48.88 per MWh.

Almost a year since the initial public call, the Ministry of Economy in Prishtina completed its pilot solar power auction. Even though it raised the ceiling price in late December to EUR 75 per MWh from EUR 65 per MWh amid repeated delays, it was closed at EUR 48.88 per MWh.

Switzerland-based Orllati leads the winning consortium, consisting of companies from Germany and Kosovo*. The construction firm is led by Kosovar diaspora, officials said.

The victory in the electronic auction translates to the right to take land on lease for a photovoltaic park of 90 MW to 105 MW in total connection capacity and up to 117 MW in peak terms. Orllati agreed to build and operate the facility for 30 years, of which the first 15 years it would sell electricity under a contract for difference (CfD) equalling the winning price.

The government-owned land is in the cadastral zones of Kramovik and Petković (Guri i Kuq) in the municipality of Rahovec or Orahovac.

Auction terms were amended ten times

Two Turkish consortia participated in the auction – Çalik and Limak, and Güri̇ş İnşaat ve Mühendislik (Güri̇ş Construction and Engineering) – together with Akuo Energy, headquartered in France, and Egypt-based Elswedy Electric. It consisted of four rounds, the ministry said. The first one, with 43 bids, drove the price down to EUR 57 per MWh while the final level was reached in the third one.

Kosovo* intends to launch auctions this year for 45 MW in battery storage and 150 MW in wind power

Minister of Economy Artane Rizvanolli said the competitive process is ensuring affordability for citizens, strengthening the security of supply and the sector’s sustainability and enabling private investments. She revealed that the auction terms were amended ten times in line with investors’ suggestions.

The winner will invest more than EUR 70 million, according to the government, which is preparing to issue calls for auctions this year for 45 MW in battery storage and 150 MW in wind power. There is 950 MW in total in the pipeline, Rizvanolli noted, saying the potential investments are valued at an overall EUR 1.2 billion.

Ceiling price at Albania’s next auction will be EUR 59.97 per MWh

The bidding was organized with the support of the United States Agency for International Development (USAID). The renewable electricity auction model was developed with the European Bank for Reconstruction and Development.

Kosovo* hosts just two operational wind power plants and some hydropower and photovoltaic capacities.

For comparison, Romania is preparing its first solar power auction for CfDs with a maximum price of EUR 91 per MWh. Amid weak participation, the lowest price at Serbia’s first solar power auction, held last year, was EUR 88.65 per MWh, just 35 eurocents below the starting level.

The maximum acceptable price in Albania’s upcoming auction is EUR 59.97 per MWh. The two previous auctions, in 2021 and 2020, were similar to the latest one in Kosovo*. The government secured land for one large-scale project at a time and for one investor each. Voltalia was the winner both for Spitalla (EUR 29.89 per MWh) and Karavasta (EUR 24.89 per MWh).

* This designation is without prejudice to positions onstatus and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.